2 additional lanes open on PR-52 in front of the Jíbaro monument.


By THE STAR STAFF
The Highways and Transportation Authority (ATH by its initials in Spanish) on Monday opened two additional lanes on the PR-52 expressway -- specifically on the stretch running from Cayey to Salinas, in front of the “Monumento al Jíbaro” -- as part of ongoing rehabilitation work in the area.
To date, the project represents an investment of $41.6 million in federal funds. The undertaking necessitated design modifications due to ground instability encountered within the affected zone.
The work was initiated following a landslide that occurred in November 2022 -- an event identified as one of the most significant of its kind ever recorded in Puerto Rico. Following that incident, an assessment of the mountainside was launched, along with efforts to stabilize the affected terrain.
Among the tasks completed is the stabilization of three slopes situated at various elevations along the mountainside. The dimensions of these areas range from nine to 49 feet, depending on the specific terrain conditions.
Work is currently continuing on the third slope, which has been described as the most complex phase of the project. Throughout this entire process, highway operations have been maintained by rerouting northbound lanes to ensure safety.
The ATH advises motorists to use the Waze app to identify alternate routes and minimize potential travel delays. Drivers are also urged to reduce their speed, remain alert to posted signage, and strictly follow the instructions provided by the traffic control devices installed within the construction zone.